Zoning and permits

Plano, Texas zoning and permits

In Plano, a commercial building opens after a chain of approvals: the City of Plano's zoning ordinance sets out "a series of 3 plans" for a development, and a Certificate of Occupancy is required to occupy any building with nonresidential uses.† † This guide lists the nonresidential districts and walks through site plans, rezoning, specific use permits, the certificate of occupancy and food permits, from the City's own documents.

Last updated

First plan review comments, commercial projects (City of Plano Building Inspections)
10 working days †
Plan review fee, as a share of the commercial permit fee, paid at submittal (City of Plano Building Inspections)
65% †
How long the Planning & Zoning Commission may table a zoning case for study (Plano zoning ordinance)
90 days †

Nonresidential districts in the zoning ordinance

The City of Plano's ordinance says "The city’s nonresidential zoning districts are listed below."† The two excerpts below print districts from that list as the ordinance prints them, with section numbers.†† The copy read for this guide is the Plano Zoning Ordinance dated September 1, 2025.† The City says its zoning layer "constitutes the City of Plano’s official zoning map." †

Plano Zoning Ordinance district list (part one) †
Map Symbol/AbbreviationDistrict NameSection
O-1Neighborhood Office10.200
O-2General Office10.300
RRetail10.400
LCLight Commercial10.500
CCCorridor Commercial10.600
UMUUrban Mixed-Use10.700
BGDowntown Business/Government10.800
CB-1Central Business-110.900
Plano Zoning Ordinance district list (part two) †
Map Symbol/AbbreviationDistrict NameSection
CECommercial Employment10.1000
RCRegional Commercial10.1100
RERegional Employment10.1200
RTResearch/Technology Center10.1300
LI-1Light Industrial-110.1400
LI-2Light Industrial-210.1500
NBDNeighborhood Business Design10.1600

Find the district on the official map before you look at a building. The district decides which uses you can put in it, and a use the table does not allow is a zoning question, not a lease question. Ordinance text is quoted as read; it may have been amended since.

What each district is for, in the ordinance's words

The ordinance says "The O-1 district is intended to provide for low-rise, garden-type office development" serving adjacent neighborhoods.† The O-2 district "is intended to allow for a variety of low-, mid-, and high-rise office developments" including "corporate offices for regional and national operations; and major centers of employment for Plano and surrounding communities." †

For shops, "The R district is primarily intended to provide areas for neighborhood, local, and regional shopping facilities", but "not including wholesaling or warehousing."† The LC district "is intended to provide for a wide array of retail, office, and service uses".† The CC district "is intended to provide for retail, service, office, and limited manufacturing uses within major regional transportation corridors." †

The ordinance says "The major focus of the CE district is to be corporate headquarters and research facilities arranged in a campus-like setting."† The RT district "is intended to create a low density, employment center consisting of office, research and development facilities, and limited assembly operations", and "RT districts should generally accommodate several users in a campus environment."†† CB-1 is "intended for use in conjunction with the CE district to permit a highly concentrated business center". †

  • UMU: "a planning, regulatory, and management framework for the design, development, and operation of urban mixed-use centers". †
  • BG: "a pedestrian-oriented center for retail, office, governmental, cultural, entertainment, and residential uses." †
  • RC: "a cultural district intended for use in conjunction with an RE district in high visibility locations". †
  • LI-1 and LI-2: areas for "light manufacturing firms" and "manufacturing firms" engaged in "processing, assembling, warehousing, research and development".† †

The ordinance also says: "Multifamily and mixed-use residential are permitted where required by state law." † If you are buying a campus or an office parcel, ask the City whether state law now opens residential uses on it. That can change what the land is worth to the next buyer.

Concept plan, preliminary site plan, site plan: the three-plan path

Plano's ordinance describes "a series of 3 plans, progressing from a general evaluation of a site and development concept to approval of a detailed development plan."† Concept plans and preliminary site plans require review and approval by the Planning & Zoning Commission.† Site plans may be approved by city staff if they conform to the preliminary plans the Commission approved. †

"Site plan approval is required prior to the release of engineering plans and building permits."† The ordinance also lists this case: "Development of a single building on one lot not exceeding 5 acres (net) and where the lot is not being subdivided from a larger property." † Count the Commission meetings into your schedule before you set a closing or a lease start date. Staff approval comes after the Commission steps, not instead of them.

  1. Step 1

    Concept plan: review and approval by the Planning & Zoning Commission †

  2. Step 2

    Preliminary site plan: review and approval by the Planning & Zoning Commission †

  3. Step 3

    Site plan: may be approved by city staff if it conforms to the approved preliminary plans †

  4. Step 4

    Engineering plans and building permits released after site plan approval †

  5. Step 5

    Certificate of Occupancy: can only be issued with an approved site plan and approved final plat filed of record, with exceptions †

Rezoning and specific use permits

The City Council changes district lines and rules by ordinance.† The ordinance says "The City Council may, from time to time, amend, supplement, or change by ordinance the boundaries of the district or the regulations herein established".† The Planning & Zoning Commission may table for study any zoning case for up to 90 days. †

A specific use permit covers uses marked "S" in the use tables.† The City Council may authorize one "after a public hearing and proper notice to all parties affected and after recommendations by the Planning & Zoning Commission".† The ordinance states the purpose: to "authorize and regulate a use not normally permitted in a district which could be of benefit in a particular case to the general welfare". † If your use carries an S in the table, budget for a public hearing and conditions. Ask what standards the City attached to similar permits before you commit to the space.

Certificate of occupancy: when you need one

City of Plano Building Inspections says a Certificate of Occupancy is required to occupy any building or property with nonresidential or multifamily uses.† It also says "A new CO is required when the occupancy, business, business name, or business ownership changes."† A second City document says a C.O. is required for change of ownership, change of tenant, and name change. †

You must "fully disclose use of the building or parcel on the application", the ordinance says.† The Planning Department reviews CO applications against the Zoning Ordinance.† A CO "can only be issued when a property has an approved site plan and approved final plat filed of record", with exceptions granted under the city's development regulations. †

City of Plano Building Inspections says that in some cases "an interior finish-out building permit is required, not a simple Certificate of Occupancy permit."† A site plan is required for "changes outside of the building, modifying parking or loading zones, and designating areas for open storage." † Before you sign a lease or buy a business, check that the building already has an approved site plan and recorded plat. If it does not, your opening date depends on fixing that first.

Commercial permits and plan review

The City of Plano's Building Inspections guide lists 10 working days for first plan review comments on a commercial project.† You submit 2 copies of required plans, scaled and dimensioned, and 3 for food related businesses.† You pay a plan review fee of 65% of the commercial permit fee at submittal. † The review clock starts on a complete package. Send scaled plans the first time, and expect comments to come back before approval.

Food service permits for restaurants

A restaurant in Plano needs a separate food service permit as well as a certificate of occupancy, according to City of Plano Building Inspections.†† Environmental Health's checklist says "All plans for any completed new construction or renovations must have been submitted to and approved by the Environmental Health plan reviewer." †

The checklist also says "All refrigeration equipment must hold at 40 °F or below with thermometers inside all units."† "The permit fees are paid to Environmental Health after the permitting inspection is passed." † Restaurant tenants run two tracks at once: building permits and health plan review. Start the health review early so the two finish together.

Questions about Plano zoning and permits

Do I need a certificate of occupancy for a commercial space in Plano?

Yes. City of Plano Building Inspections says a Certificate of Occupancy is required to occupy any building or property with nonresidential or multifamily uses. †

If I buy a business in Plano, do I need a new CO?

Yes. City of Plano Building Inspections says "A new CO is required when the occupancy, business, business name, or business ownership changes." †

Who approves a site plan in Plano?

It depends on the plan. Plano's zoning ordinance says concept plans and preliminary site plans require review and approval by the Planning & Zoning Commission, and that site plans may be approved by city staff when they conform to the preliminary plans the Commission approved. ††

How long does commercial plan review take in Plano?

The City of Plano's Building Inspections guide lists 10 working days for first plan review comments on a commercial project. †

What is the plan review fee for a commercial permit in Plano?

65% of the commercial permit fee, paid at submittal, according to the City of Plano's Building Inspections guide. †

Does a restaurant in Plano need more than a certificate of occupancy?

Yes. City of Plano Building Inspections says a separate food service permit is required for restaurants and other food service businesses. †

Can the Planning & Zoning Commission delay a zoning case in Plano?

Yes. Plano's zoning ordinance says the Commission may table for study any zoning case for up to 90 days. †

Who publishes this site, and whether it names an agent, is answered on the FAQ page.

Next step

Zoning tells you what a parcel allows. The land guide covers where undeveloped commercial land is and what the City's plan wants on it.